November 13, 2026 — Barcelona-El Prat (BCN), one of Spain’s busiest airports, will run on a single runway from Monday, November 16, through Thursday, November 26, while Aena builds a new high-speed exit on its cross runway.
During those 11 days, the cross runway 02/20 and the parallel runway 06L/24R will both be closed, leaving only the coastal runway, 06R/24L, in use. Aena says it planned the closures with the airlines and has withdrawn 1,441 slots, about 15% of the airport’s capacity for the period. It has not said which airlines or flights are affected.
The €3.1 million project will take about 12.5 months. Night-time runway closures from 11 p.m. to 7 a.m. began earlier this fall and will continue, but November 16–26 is the only stretch with a major cut in capacity.
| Item | Detail |
|---|---|
| Single-runway period | Nov. 16–26, 2026 |
| Runways closed | 02/20 and 06L/24R |
| Runway open | 06R/24L |
| Slots withdrawn | 1,441 (about 15%) |
| Project length | About 12.5 months |
What it means for travelers
- With roughly 15% fewer slots, some BCN flights have been trimmed or retimed. Check your booking for schedule changes now.
- Single-runway operations mean delays and missed connections are more likely at peak times, so avoid tight onward connections.
- This overlaps Spain’s Nov. 17 rail strike date. Plan a backup way into and out of the city.
Sources
- Aena — press release on the new rapid exit on runway 02/20 at Barcelona-El Prat (Sept. 18, 2026)
- Rus Tourism News — Barcelona Airport will operate with one runway Nov. 16–26
- ENAIRE — AIP Supplement SUP 142/26 (LEBL)